# Run Production

A **run** is a stretch of time your machine spends making one product. Kanoa measures everything against the run: the
count, the rate and the OEE. This lesson shows you how to start a run, follow how it's doing, and end it.

You start and end runs from **Run Control**. Opening it needs the **Operate Assets** security function.

## Open Run Control

Tap the **Production** card at the top of the info panel. It shows the machine's current mode, such as *Idle*. Run
Control opens as a popup.

::embed-section{src="../../kanoa-ops/asset-operation.md#start-and-end-runs-run-control"}

## Start a Run

Your plant runs either from **production orders** (each order says what to make and how many) or straight from a
**product**. Use whichever your supervisor has told you to.

### From a Production Order

1. In Run Control, select the **Orders** tab. It lists the orders you can start on this machine.
2. Select the order you're starting.
3. Click **Start Run**, then close Run Control.

If the order you expect isn't on the list, it may not be released yet, or it may be scheduled on another machine. Ask your
supervisor or scheduler.

### From a Product

1. In Run Control, select the **Product** tab.
2. Select the product you're making.
3. Click **Start Run**, then close Run Control.

Either way, the **Production** card now shows *Production* with the product and order, and the **State** card shows
whether the machine is running.

:::note
Some plants add a step before a run starts, such as a setup checklist or setpoints to confirm. If a popup opens when you
click **Start Run**, follow it through: it's your plant's own step, and the run starts when you finish it.
:::

## Follow the Run

While the run goes, keep an eye on the **Current Run** tab under the cards:

- **Output**: how much you've made, at what rate, and how much was wasted.
- **KPIs**: your count against the target, your rate against the standard rate, and OEE.

If the machine runs slower than its standard rate, a **Speed loss** card appears on the info panel, saying how far below
it is. You'll see how to give it a reason in [Record Downtime](./3-record-downtime.md).

## End a Run

When the order is finished, or you stop making the product:

1. Tap the **Production** card to open Run Control.
2. Select the **Mode** tab, and select the mode that matches what the machine does next: **Idle** if it's waiting, or
   **Changeover** if you're setting up for the next product.
3. Click the button at the top of Run Control to change to that mode, then close Run Control.

Changing the mode ends the production run. Time in a mode such as **Idle** or **Maintenance** isn't counted against your
run's OEE.

{/*
TODO: confirm the label of the button at the top of Run Control when a mode is selected on the Mode tab.
*/}

## Check Your Understanding

1. Where do you start a run?
2. The order you need isn't on the Orders tab. What are two reasons that could be?
3. You've finished an order and the machine will sit waiting for material. What mode do you put it in?

<details>
<summary>Answers</summary>

1. In **Run Control**, opened by tapping the **Production** card.
2. The order isn't released for production yet, or it's scheduled on another machine.
3. **Idle**.

</details>