Skip to main content

Preventive Maintenance

Preventive maintenance (PM) is work that happens on a regular interval, such as every week. Kanoa creates each PM work order for you from a schedule, so there's nothing to raise. You find it in your list and do it. For example, Machine 1 - Weekly PM comes up once a week, if it has been created: the Maintenance Manager track schedules it in Plan Preventive Maintenance.

Find the PM Work Order​

  1. Open Maintenance → Work Orders.
  2. Use the Select Type... filter to show Preventive work, or search for the title.
  3. Open the PM work order for your machine.

A PM work order can show up before its due date. The schedule can create work orders ahead of time, so planners and technicians see next week's workload coming. Check the Due on date, not just whether the work order exists.

Complete the PM​

A PM work order usually carries a procedure, so you work it step by step.

  1. Assign the work order to yourself if it isn't yours, and click In Progress.
  2. Open the Procedure tab. Each step is a button that shows how many checks it has.
  3. Work through the checks in each step. If something fails, mark the check as Not OK and add a comment.
  4. Enter the Time Taken for each step.
  5. Click Completed.

The time you enter on each step is reported as procedure step hours, with the technician time you log on the work order.

See When It Comes Due Next​

A recurring schedule makes the next work order on its own. You see when it's next due by finding it in the list.

  1. In Maintenance → Work Orders, look for the next PM work order for the same asset.
  2. Read its Due on date on the card, or its Due Date in the panel.

Schedule times follow the asset's site time zone, so a PM due at 06:00 stays at 06:00 at the plant when the clocks change.

Reference Materials: Schedule Types - One Time, Recurring and Condition work orders.

Schedule Types​

A Work Order template includes a Schedule Type, which determines how work orders are generated. When a template is active i.e. 'Released', the system evaluates its schedule configuration. When the criteria are satisfied, an actual work order is created.

Kanoa Maintenance supports three primary schedule behaviors:

One Time

Use One Time when the template should generate a single work order.

This is useful for:

  • one-off repairs
  • installation work
  • project tasks
  • ad hoc maintenance requests

When a template is configured as One Time, the system generates one actual work order from that template.

Recurring

Use Recurring when the template should continuously generate work orders on a defined schedule.

This is typically used for:

  • preventive maintenance
  • routine inspections
  • repeating safety checks
  • calendar-based maintenance programs

When a template is configured as Recurring, the system creates actual work orders according to the recurrence settings. The schedule's times are in the asset's site time zone (UTC if the site has none), so a work order due at 06:00 stays at 06:00 at the plant across daylight-saving changes.

Recurring schedules are best used when maintenance should happen on a predictable interval, such as:

  • every day
  • every week
  • every month
  • every X days/hours depending on schedule configuration

kanoa-cmms

Condition

Use Condition when the template should generate work orders only after a defined asset condition, counter, or threshold is met.

This is typically used for:

  • runtime-based maintenance
  • counter-based maintenance
  • threshold-triggered inspections
  • condition-based corrective or preventive work

When a template is configured as Condition, the maintenance order can be set to be triggered whenever the asset run hours or counter values reach a certain threshold, or, for a tool, when its tool life comes due. Condition scheduling is useful for maintenance strategies that should not be driven by calendar date alone.


kanoa-cmms


kanoa-cmms


Tool Life works with Kanoa Ops tooling. It's only offered when the template's Asset is a tool, such as a mold, so select the tool first. Set Due for to the tool limit the work order covers: its PM, refurbishment or calibration. A work order is created when the tool reaches its Warn at % of that limit, and completing the work order resets that count, the same as recording it on the tool's Life tab. The tool's work orders are listed on the Maintenance tab of its tool editor.


kanoa-cmms


Check Your Understanding​

  1. Do you have to create a PM work order each week?
  2. A step's check fails. What do you do on the Procedure tab?
  3. Where do you read when the next PM is due?
Answers
  1. No. A recurring schedule creates each PM work order for you.
  2. Mark the check Not OK and add a comment.
  3. On the next PM work order for the asset, in the Due on date on its card or the Due Date in the panel.